DOE closes ATVM loan for Thacker Pass lithium processing facilities
- USUnited States
- evt-us-doe-thacker-pass-loan-2024
Policy statusActive
- Jurisdiction
- United States
- Issuing authority
- U.S. Department of Energy, Loan Programs Office
- Document number
- DOE ATVM Loan No. A1034
- Mechanism
- Funding or subsidy, Supply-chain security measure
- Sectors
- Battery, Energy, Industrial
- Affected materials
- Sources
- 5
- Instruments
- 1 financial, 0 control
Summary
DOE executed an Advanced Technology Vehicles Manufacturing loan agreement on 28 October 2024 with Lithium Nevada Corp. (later Lithium Nevada LLC) to finance Thacker Pass Phase 1 lithium-carbonate processing facilities and related infrastructure in Nevada, excluding the open-pit mine itself. The original approximately $2.26 billion facility ($1.97 billion principal and estimated capitalized interest) was amended in October 2025 to approximately $2.23 billion; three advances totaled $1.209 billion by 30 June 2026. The financing is a single executed and partially disbursed facility, not two loans or four separate commitments. SEC reporting separately establishes ongoing processing-plant construction.
Analytical significance
A large U.S. industrial-finance intervention with distinct legal closing, amended cap, repeated cash advances and verified physical construction. The DOE/FFB loan financing is focused on domestic conversion of lithium-bearing ore into battery-grade lithium carbonate, not federal financing of mine development. Preserve the distinction between announced capacity, binding financing, partial disbursement, and actual construction.
Framing anchors
Framing: Not yet coded. A verified quotation from the primary source is still needed before assigning a framing category.
Paid, promised or conditional
DOE closes ATVM loan for Thacker Pass lithium processing facilities, 28 October 2024. Status of each line as of 12 November 2026.
- Partly disbursedSome money is recorded as paid. The amount shown is the commitment, not the cash paid.
Status by date
Provider
Relationship
Recipient
Selected
Select a line or an organization to read its details here.
All flows
Partly disbursed
U.S. Department of Energy to Lithium Nevada LLC
About USD 2.23 billion, loanPartially disbursed 20 Oct 2025. The amount shown is the commitment, not the cash paid.View details
- KindPartly disbursed. The amount shown is the commitment, not the cash paid.
- InstrumentLoan. Recorded as: commitment. Capital source: public.
- Amount as statedabout USD 2.23 billion (source wording: “$2.23 billion amended expected loan amount ($1.97 billion principal plus approximately $256 million capitalized interest)”)
- Status on 12 November 2026Partially disbursed 20 Oct 2025First $435M DOE-loan advance received on 20 October 2025. Issuer's 2026 Q2 filing confirms subsequent draws of $432M (24 February 2026) and $342M (3 June 2026), totaling $1.209B advanced by 30 June 2026. These are draws under the same facility, not additive commitments.Status stated by Lithium Americas Corp. / U.S. Securities and Exchange Commission (EDGAR): Lithium Americas Corp., Form 10-Q for the quarter ended 30 June 2026
- FromU.S. Department of Energy
- ToLithium Nevada LLC
- ProjectThacker Pass Phase 1 lithium-carbonate processing facilities
- FinancingView details
- SourcesThacker Pass — DOE Loan Programs Office project and financial summary; EIS-0561 Thacker Pass loan: DOE processing-facility-only scope and 28 October 2024 decision; Lithium Americas, Exhibit 10.11 — 28 October 2024 ATVM Loan Arrangement and Reimbursement Agreement; Lithium Americas, Exhibit 10.1 — 7 October 2025 omnibus DOE loan amendment; Lithium Americas Corp., Form 10-Q for the quarter ended 30 June 2026; Lithium Americas Form 8-K — 7 October 2025 DOE amendment subject to conditions
Each amount is quoted as its source states it, in the original currency, and no amount is added to another. Line style shows the kind of relationship, not the size of the amount.
Sources: Thacker Pass — DOE Loan Programs Office project and financial summary; EIS-0561 Thacker Pass loan: DOE processing-facility-only scope and 28 October 2024 decision (28 Oct 2024); Lithium Americas, Exhibit 10.11 — 28 October 2024 ATVM Loan Arrangement and Reimbursement Agreement; Lithium Americas, Exhibit 10.1 — 7 October 2025 omnibus DOE loan amendment; Lithium Americas Corp., Form 10-Q for the quarter ended 30 June 2026 (13 Aug 2026); Lithium Americas Form 8-K — 7 October 2025 DOE amendment subject to conditions (8 Oct 2025).
Instruments in this event
Financial instruments (1)
Lithium Nevada LLC (formerly Lithium Nevada Corp.)
Thacker Pass Phase 1 lithium carbonate processing facilities
aboutUSD2.23 billionPartially disbursed20 Oct 2025- Providing government
- US
- Value role
- Commitment
- Instrument
- Loan
- Capital source
- Public
- Supply-chain stages
- Processing
Sources5
Thacker Pass — DOE Loan Programs Office project and financial summary
Primary sourceU.S. Department of Energy, Loan Programs Office
Official DOE project page, marked last updated October 2024: $2.26 billion ATVM direct-loan facility including $1.97B principal and about $289.7M capitalized interest, borrower then Lithium Nevada Corp, Phase 1 lithium-carbonate processing facilities in Humboldt County, Nevada. This is original closing-era amount and should not be used as the 2026 amended amount or as a disbursement.
https://www.energy.gov/edf/thacker-pass
EIS-0561 Thacker Pass loan: DOE processing-facility-only scope and 28 October 2024 decision
Primary sourceU.S. Department of Energy
DOE NEPA explanation specifies that the proposed loan covers Thacker Pass mine processing facilities and associated infrastructure, not the development and operation of the open-pit mine. DOE Record of Decision issued 28 October 2024.
https://www.energy.gov/nepa/doeeis-0561-thacker-pass-lithium-mine-project
Lithium Americas, Exhibit 10.11 — 28 October 2024 ATVM Loan Arrangement and Reimbursement Agreement
Primary sourceLithium Americas Corp. / U.S. Securities and Exchange Commission (EDGAR)
Executed Loan Arrangement and Reimbursement Agreement dated 28 October 2024, loan number A1034, between DOE and LITHIUM NEVADA CORP. as Borrower. Federal Financing Bank advance arrangements occur under the ATVM legal mechanics, not as another project loan. Document exhibited to issuer SEC filing in 2025; agreement date is not its SEC publication date.
https://www.sec.gov/Archives/edgar/data/1966983/000095017025046424/lac-ex10_11.htm
Lithium Americas, Exhibit 10.1 — 7 October 2025 omnibus DOE loan amendment
Primary sourceLithium Americas Corp. / U.S. Securities and Exchange Commission (EDGAR)
Omnibus Waiver, Consent and Amendment No. 2 dated as of 7 October 2025 identifies LITHIUM NEVADA LLC (formerly Lithium Nevada Corp.) as the same Nevada borrower and Lithium Americas Corp as Sponsor. A revised legal agreement to the existing 2024 facility, not a second DOE loan. Published as an issuer exhibit in 2026.
https://www.sec.gov/Archives/edgar/data/1966983/000119312526115081/lac-ex10_1.htm
Lithium Americas Corp., Form 10-Q for the quarter ended 30 June 2026
Primary sourceLithium Americas Corp. / U.S. Securities and Exchange Commission (EDGAR)
DOE Loan Note 4 and MD&A pages 23–28: original 2024 loan $2.26B ($1.97B principal plus estimated $289.6M interest), amended Oct 7 2025 expected total $2.23B ($1.97B principal plus estimated $256M interest). Three cash advances $435M Oct 20 2025, $432M Feb 24 2026, $342M Jun 3 2026; cumulative advances $1.209B by Jun 30 2026. This cumulative amount is within, not in addition to, the facility; carrying amount $988.018M reflects debt costs and accrued interest and is not cumulative cash advanced. Thacker Pass Phase 1 plant construction ongoing, not operational.
https://www.sec.gov/Archives/edgar/data/1966983/000119312526347826/lac-20260630.htm
Cite this page
This cites Stratellar's coding of the instrument. For a claim about what a government actually did, cite the primary document itself; the sources above carry the canonical URLs.
Stratellar. "DOE closes ATVM loan for Thacker Pass lithium processing facilities." Record evt-us-doe-thacker-pass-loan-2024, 2024-10-28. https://stratellar.com/events/evt-us-doe-thacker-pass-loan-2024