DOE closes $996 million loan guarantee for Rhyolite Ridge lithium processing
- USUnited States
- evt-us-doe-rhyolite-ridge-2025
Policy statusActive
- Jurisdiction
- United States
- Issuing authority
- U.S. Department of Energy, Loan Programs Office
- Document number
- Not yet coded
- Mechanism
- Funding or subsidy, Supply-chain security measure
- Sectors
- Battery, Energy, Industrial
- Affected materials
- Sources
- 6
- Instruments
- 1 financial, 0 control
Summary
On 17 January 2025 DOE closed an ATVM loan guarantee of $996 million ($968 million principal and $28 million capitalized interest) to Ioneer Rhyolite Ridge LLC for on-site lithium carbonate processing at the Rhyolite Ridge project in Nevada. The guarantee is a signed financing facility, not a disbursement, and DOE financing is restricted to the processing plant and related infrastructure, not the open-pit mine. As of June 2026 the issuer remained pre-final-investment decision with equity partner and additional financing requirements, with no substantiated DOE advance.
Analytical significance
Shows a binding U.S. industrial-finance commitment that remains short of funded physical implementation. Separate the closed loan guarantee from the older conditional loan proposal, third-party equity, cash advances, and future mine/processing construction. The U.S. borrower is distinct from the Australian public parent.
Framing anchors
Framing: Not yet coded. A verified quotation from the primary source is still needed before assigning a framing category.
Paid, promised or conditional
DOE closes $996 million loan guarantee for Rhyolite Ridge lithium processing, 17 January 2025. Status of each line as of 12 November 2026.
- Contingent or optionalNo money is committed unless an option is exercised, a trigger is met or a binding agreement follows.
Provider
Relationship
Recipient
Selected
Select a line or an organization to read its details here.
All flows
Contingent or optional
U.S. Department of Energy to Ioneer Rhyolite Ridge LLC
USD 996 million, loan guaranteeContracted 17 Jan 2025. A guarantee, which pays only if it is called.View details
- KindContingent or optional. A guarantee, which pays only if it is called.
- InstrumentLoan guarantee. Recorded as: commitment. Capital source: public.
- Amount as statedUSD 996 million (source wording: “$996 million loan guarantee ($968 million principal plus $28 million capitalized interest)”)
- Status on 12 November 2026Contracted 17 Jan 2025DOE's 17 January 2025 announcement expressly reports closing the $996M ATVM loan guarantee to Ioneer Rhyolite Ridge LLC. Funding is subject to conditions precedent; no positive advance evidence in reviewed June–August 2026 issuer filings. The 2023 conditional loan is not a second count.Status stated by U.S. Department of Energy, Loan Programs Office: DOE closes $996 million loan guarantee for Ioneer Rhyolite Ridge
- FromU.S. Department of Energy
- ToIoneer Rhyolite Ridge LLC
- ProjectRhyolite Ridge on-site lithium processing facilities
- FinancingView details
- SourcesDOE closes $996 million loan guarantee for Ioneer Rhyolite Ridge; Ioneer January 2025 SEC exhibit — $996 million DOE loan closing; DOE/EIS-0565 — Rhyolite Ridge mine processing loan scope; Ioneer Transition Form 20-F (2026) — Rhyolite Ridge financing conditions and pre-FID status; Ioneer 30 July 2026 Quarterly Activities Report — Rhyolite Ridge remains pre-FID; Ioneer half-year financial statements ended June 30, 2026 (SEC Exhibit 99.1)
Each amount is quoted as its source states it, in the original currency, and no amount is added to another. Line style shows the kind of relationship, not the size of the amount.
Sources: DOE closes $996 million loan guarantee for Ioneer Rhyolite Ridge (17 Jan 2025); Ioneer January 2025 SEC exhibit — $996 million DOE loan closing (17 Jan 2025); DOE/EIS-0565 — Rhyolite Ridge mine processing loan scope; Ioneer Transition Form 20-F (2026) — Rhyolite Ridge financing conditions and pre-FID status (29 Apr 2026); Ioneer 30 July 2026 Quarterly Activities Report — Rhyolite Ridge remains pre-FID (30 Jul 2026); Ioneer half-year financial statements ended June 30, 2026 (SEC Exhibit 99.1) (13 Aug 2026).
Instruments in this event
Financial instruments (1)
Ioneer Rhyolite Ridge LLC
Rhyolite Ridge on-site lithium processing facility
USD996 millionContracted17 Jan 2025- Providing government
- US
- Value role
- Commitment
- Instrument
- Loan guarantee
- Capital source
- Public
- Supply-chain stages
- Processing
Sources6
DOE closes $996 million loan guarantee for Ioneer Rhyolite Ridge
Primary sourceU.S. Department of Energy, Loan Programs Office
Closing announcement: $996M guarantee, $968M principal plus $28M capitalized interest, to Ioneer Rhyolite Ridge LLC under ATVM. DOE specifies on-site lithium-carbonate processing and identified ioneer Ltd as developer; Jan 2025 closing is not evidence of cash advanced, operating production or mine financing.
https://www.energy.gov/edf/articles/doe-announces-996-million-loan-guarantee-ioneer-rhyolite-ridge-advance-domestic
DOE/EIS-0565 — Rhyolite Ridge mine processing loan scope
Primary sourceU.S. Department of Energy, NEPA
DOE environmental summary explicitly confines contemplated federal loan to on-site lithium processing facilities, sulfuric acid plant and supporting infrastructure, NOT open-pit mine development/operation. The early NEPA synopsis calls the proposed borrower Rhyolite Ridge Holdings LLC; do not conflate that with the closing release's Ioneer Rhyolite Ridge LLC without legal proof.
https://www.energy.gov/nepa/doeeis-0565-rhyolite-ridge-lithium-boron-project-esmeralda-county-nevada
Ioneer January 2025 SEC exhibit — $996 million DOE loan closing
Primary sourceIoneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
Issuer's 17 January 2025 closing announcement confirms the $996M ATVM facility, principal/interest split and earlier January 2023 conditional offer, including $268M principal increase. This is the same loan, not a second 2023 commitment or $996M immediately paid.
https://www.sec.gov/Archives/edgar/data/1896084/000114036125001367/ef20041815_ex99-1.htm
Ioneer Transition Form 20-F (2026) — Rhyolite Ridge financing conditions and pre-FID status
Primary sourceIoneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
Issuer securities filing recounts 2025 loan closing and conditions to first DOE advance (strategic partner equity, additional funding and project-finance model), and states that a final investment decision and construction need further financing. The February 2025 Sibanye proposal did not proceed; it is not a valid assumption of equity capital.
https://www.sec.gov/Archives/edgar/data/1896084/000114036126017853/ef20070398_20f.htm
Ioneer 30 July 2026 Quarterly Activities Report — Rhyolite Ridge remains pre-FID
Primary sourceIoneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
June 2026 quarter update: strategic partner and Final Investment Decision still outstanding; pre-feasibility for battery-grade lithium carbonate completed, construction remains a future milestone; expressly confirms no production or development activity in quarter. Nonbinding Korea KIND/Hyundai MOUs are not cash or binding equity. Separate US Army Tooele land-lease possibility is not part of this ATVM guarantee.
https://www.sec.gov/Archives/edgar/data/1896084/000114036126030118/ef20078896_ex99-1.htm
Ioneer half-year financial statements ended June 30, 2026 (SEC Exhibit 99.1)
Primary sourceIoneer Ltd / U.S. Securities and Exchange Commission (EDGAR)
Directors' report: issuer compliant with closed DOE loan facility, no development decision at June 30, 2026. Note 10: $4.273M unamortized DOE loan establishment fees, amortization starts after first draw; it is not an advance or independent commitment. Filing documents no positive disbursement; an absence of disclosure is not a universal proof none occurred later.
https://www.sec.gov/Archives/edgar/data/1896084/000114036126032597/ef20079527_ex99-1.htm
Cite this page
This cites Stratellar's coding of the instrument. For a claim about what a government actually did, cite the primary document itself; the sources above carry the canonical URLs.
Stratellar. "DOE closes $996 million loan guarantee for Rhyolite Ridge lithium processing." Record evt-us-doe-rhyolite-ridge-2025, 2025-01-17. https://stratellar.com/events/evt-us-doe-rhyolite-ridge-2025