Tungsten Supply Security

Policy, financing and industrial development across China, the EU, the UK and Japan.

By Benjamin Yang · Research cutoff

A lustrous dark tungsten-bearing mineral crystal with fine parallel ridges against a black background.
A tungsten-bearing mineral specimen photographed for the USGS, United States Geological Survey collection, . This mineral specimen is illustrative and does not document production at any project discussed in the research.USGS tungsten photo-contest image. Carlin Green, U.S. Geological Survey. Rights.

According to the US Geological Survey's rounded estimates, China accounted for about 79% of mined tungsten content worldwide in 2025. For buyers, that concentration extends beyond the mine: tungsten must also move through chemical conversion, powder production and fabrication before it reaches many industrial users. Securing ore alone does not guarantee a usable supply.

Across China, the European Union, the United Kingdom and Japan, governments are pursuing different ways to secure that supply. Some regulate exports. Others back mines, support processing capacity or designate projects for faster administrative treatment. Looking at the financing and company disclosures alongside the official measures shows how far each effort has moved toward production.

Policy instruments and recorded implementation

Selected tungsten policy measures in China, the European Union, the United Kingdom and Japan
JurisdictionInstrumentDocumented implementation
ChinaExport licensingControls on specified tungsten products and technologies introduced in February 2025
European UnionStrategic Project designationEl Moto under construction; separately designated APT plant at proposal stage
United KingdomEquity and lending£25 million Hemerdon core loan reported fully drawn by 2 September 2026
JapanIndustrial grantsGrant decisions for tungsten powder, carbide and recycled-feedstock conversion projects

Hemerdon's £71 million package includes a loan that must be repaid

In August 2026, the UK's National Wealth Fund announced up to £71 million for Tungsten West's Hemerdon restart: £36 million in equity, a £25 million core loan and another £10 million of potential lending under an accordion facility. The final £10 million depends on a further commitment, so the headline package is larger than the financing already arranged. The company's accounts provide a separate check on how much of the core loan was drawn.

Tungsten West reported that the £25 million core loan was fully drawn by 2 September 2026, when its FY2026 accounts were approved. With the financial year having ended on 31 March, the accounts recorded this as a subsequent event. They establish that the financing had been drawn by the approval date, although they do not identify the exact transfer date.

The mix of equity and borrowing matters as Hemerdon moves toward production. The August terms describe a proposed secured loan with a short maturity and escalating interest, while the wider £88 million funding plan also accounts for bridge-finance repayment and forecast revenue. How much public money adds to actual mine spending depends on where the proceeds go and what financing would otherwise have been available.

Processing at Hemerdon began before the August funding announcement

Tungsten West's accounts and August announcement describe commissioning and initial concentrate activity in July 2026, ahead of the public financing announcement on 25 August. Ore processing was already under way as the funding package was being announced. That sequence matters when attributing the restart's operational progress to government financing.

The prospect of public support may have informed decisions made earlier, and drawn funds can help pay for the subsequent ramp-up. The disclosed record establishes processing activity and full core-loan drawdown, but does not show how much extra production the loan itself made possible. Sustained output and customer deliveries are the next useful measures of the restart.

In September, Tungsten West announced a binding eight-year tungsten offtake agreement with Elmet, with variable pricing linked to APT benchmarks. Elmet furnished its 22 September release as Exhibit 99.1 under Item 7.01 of an SEC Form 8-K. The deal gives the mine a contracted route to an allied conversion partner. Its commercial value will become clearer once concentrate is delivered, processed and paid for.

EU tungsten projects are at very different stages

Under the EU Critical Raw Materials Act, Strategic Project designation can help qualifying projects navigate permitting and financing channels. The selected tungsten projects span extraction, processing and recycling, but receiving the same designation does not mean they are equally close to production.

El Moto received recognition in March 2025. Its developer described the mine as under construction in 2026 and targeted first production in the first quarter of 2029. The EU APT Tungsten Plant, added to the October 2026 list, was still being evaluated for potential technical partnerships, with a final investment decision pending. These are different starting points for measuring what designation achieves.

Article 11 of the Critical Raw Materials Act provides permitting time limits for qualifying EU Strategic Projects, subject to specific triggers, exclusions and extensions. Those clocks concern regulatory procedures, not the time needed to build a mine or plant. The October decision was adopted on 9 October and published on 22 October 2026; its notification date still requires verification under EU law.

For either project, the more useful evidence will be a permitting decision, financing close or construction milestone. Those records can show whether designation helped a project advance beyond its status when it was selected.

Japan is funding the conversion stages of tungsten supply

Japan's supported projects focus on turning tungsten inputs into materials manufacturers can use. Allied Material plans new powder and tungsten-carbide equipment and a plant intended to lift capacity to roughly 1.5 times the existing level, with operations targeted for the first half of fiscal 2028. Japan New Metals plans to expand its Akita operation to process scrap into ammonium paratungstate (APT).

JOGMEC lists grant decisions of approximately ¥7.5 billion for Allied Material and ¥2 billion for Japan New Metals. The latter is a more advanced funding status than the earlier announcement captured in SMPT's frozen project data. Still, an award decision and a paid grant are different events; neither by itself establishes that equipment has been installed or additional tungsten has been produced.

Mitsubishi Materials reports about ¥8 billion in planned investment for the Japan New Metals programme and a target of 2,400 tonnes of annual APT capacity, expressed as WO3 equivalent, with operations scheduled for April 2029. The figure is planned total capacity in a specified chemical equivalent, which matters when comparing it with production targets for other tungsten products.

China's tungsten controls depend on the specific product

China's Announcement No. 10 of 4 February 2025 requires export permission for specified tungsten products and production technologies. Its coverage includes particular forms of APT, oxides, carbides, solid tungsten and alloys, with technical thresholds for some items. Those specifications determine which exports fall under the rule.

To understand how the controls affect trade, the next evidence needed is item-specific: licence applications, approvals and denials, processing times, enforcement records and shipments. Mine construction figures address a different question.

What will show whether the projects deliver

For Hemerdon, the test is sustained production and accepted deliveries alongside the loan's repayment schedule. For Japan's conversion plants, grant awards will need to be followed by spending, installation and saleable output. EU designations will matter most when projects obtain permits, finance and construction progress. China's licensing system needs to be assessed through actual transactions.

This comparison draws on SMPT data frozen at commit `4fc59c7ea38ca788eb7537353274a953c90e13eb` and official and corporate disclosures available through 3 November 2026. The selected records cover 11 events, eight projects, eight designations, six financing rows and two control clauses. Several refer to the same underlying projects or interventions, so the record counts are not counts of independent outcomes.

Across the four markets, the point at which a policy becomes useful to a buyer varies. A licence decision, a loan drawdown and a plant opening each show a different stage of implementation. Ultimately, reliable supply will depend on whether the relevant material reaches customers in a usable form and on workable commercial terms.

Research record

Research cutoff: 3 November 2026. The comparison uses the SMPT dataset frozen at GitHub commit 4fc59c7, supplemented by the original sources linked above. The complete dossier contains the supporting exhibits, original-source register and methodology.

Suggested citation: Yang, Benjamin. “Tungsten Supply Security.” Strategic Materials Policy Tracker, Research Dossier 001 (November 2026).