Qualify another supplier before committing to five months of stock
In the model’s severe 2030 case, an eight-month supply interruption can be covered with five months of inventory and an initial stock purchase of about $2.30 million, provided the alternative supplier qualifies. A nine-month, inventory-led approach also covers the disruption, but would tie up about $4.13 million—above the hypothetical buyer’s $3 million cash ceiling.
That five-month plan assumes the manufacturer can qualify a separate supplier for 45% of its international sourcing, including checks on grade, refining origin, end-use eligibility and delivery terms. Without that channel, the same strategy would leave 16.5 metric tons of modeled demand unfilled during the severe 2027 interruption.
U.S. import dependence makes supplier qualification important
The US Geological Survey estimated that the United States relied on net imports for 91% of its antimony in 2025. China accounted for 55% of U.S. antimony metal and oxide imports over 2021–2024. Those national figures help explain the exposure, but a manufacturer still has to confirm whether a proposed supplier can deliver the right grade and form, with verified refining history and products that pass acceptance testing.
New domestic supply could eventually reduce that exposure. EXIM lists $2.906 billion for the Stibnite project as authorized, while Idaho National Laboratory’s 2026 pilot commissioning shows early processing capability. Authorization is not a financing close, and a commissioned pilot is not the same as qualified antimony arriving at a manufacturer’s plant. Both projects need further commercial milestones before a buyer can rely on deliveries.
The balanced option stays within the modeled cash and supply limits
The table assumes a manufacturer using 100 metric tons of contained antimony each year, an eight-month severe interruption in 2030, and the qualified supplier mix and domestic availability specified in the model.
| Strategy | Stock buffer | Unfilled | Stock cash | Annual increment |
|---|---|---|---|---|
| Domestic-led | 2 mo | 22.1 t | $0.92m | $768k |
| Diversification-led | 3 mo | 16.7 t | $1.38m | $773k |
| Inventory-led | 9 mo | 0 t | $4.13m | $703k |
| Balanced / conditional | 5 mo | 0 t | $2.30m | $813k |
Stock purchases remain inventory assets. The annual extra cost includes the model’s sourcing premiums, holding costs and emergency purchase markups. Figures are rounded from the linked workbook.
What a manufacturer would need to confirm
- Supplier qualification. Procurement and engineering teams would verify the grade, refinery, shipment origin, licensing requirements, storage conditions and delivery capacity before relying on the alternative source.
- Inventory funding. Finance would check the actual purchase price, storage and replenishment costs against available cash. The case includes a sixth-month purchase option if five months of stock proves insufficient.
- Domestic offtake. Any future U.S. sourcing share would depend on documented financing and processing progress, tested product and enforceable delivery terms.
Sources and assumptions
The case uses Stratellar’s antimony records alongside USGS estimates, government financing and licensing records, laboratory reporting and company filings. It treats announced projects, authorized financing, payments and commercial deliveries as separate events.
The manufacturer, its annual demand, sourcing shares, premiums, inventory ceiling and disruptions are hypothetical. The accompanying workbook tests what these assumptions would mean for costs and unfilled demand; it does not project an actual buyer’s future supply.
Selected original sources
- USGS Mineral Commodity Summaries 2026 — Antimony
- EXIM project-finance transaction register
- Perpetua Resources June 2026 Form 10-Q
- Idaho National Laboratory antimony processing pilot
- MOFCOM/GACC antimony export licensing, Announcement 33
- MOFCOM Announcement 46 — U.S. military-end-use rule
- MOFCOM Announcement 72 — temporary clause suspension
Research and source retrieval: 4 November 2026. Suggested citation: Yang, Benjamin. “U.S. Antimony Supply Resilience, 2027–2031.” Strategic Materials Policy Tracker, Applied Strategy 001 (November 2026).