Allied Material tungsten reduction and carburisation facilities
- JPJapan
- prj-jp-almt-tungsten
Latest financing-row activity reportAnnounced株式会社アライドマテリアル (A.L.M.T. Corp.)
- Sponsors
- Allied Material CorporationCompany
- Location
- 富山製作所から約1kmの場所JP
- Stages
- Processing
- Materials
- TungstenTracked materials only
- Co-investment
- Public capital and a designation
What does the record establish?
METI's certified-plan list does not state a location. The recipient's 9 April 2026 release identifies a new site about 1 km from Toyama Works. Site secured does not establish construction commencement, ownership of the land, or operation.
Financial standing
1 directly linked instruments. Recorded financial states: Decided. A commitment, a payment and a project cost remain separate.
Inspect instruments and termsLegal and policy context
1 parent policy actions; 1 project designations. Designation confers standing, not finance. Material and stage overlaps with controls do not establish a restriction on this project.
Read the policy actionsIndustrial evidence
No source-reviewed project milestone is published in this corpus. Financing entries may still contain attributed activity reports; this gap does not establish inactivity.
See evidence gapsFinancial evidence and chronology
Each instrument keeps its own financial history. These dates describe financial states, not construction or production. Amounts are the current recorded terms, not historical amounts at every date below.
Grant · Japan Organization for Metals and Energy Security (JOGMEC)※助成額は約75億円 · Decided · Commitment
- Provider organizations
- Japan Organization for Metals and Energy Security (JOGMEC)
- Recipient
- 株式会社アライドマテリアルAllied Material Corporation
- Legal authority as stated
- 経済安全保障推進法 (Economic Security Promotion Act)
· Announced
METI's list gives the subsidy with the plan certified on 令和8年3月18日.
経済産業省 (Ministry of Economy, Trade and Industry, Japan)Exact status date not stated · Decided
Listed among JOGMEC's grant decisions (交付決定事業) for 令和7年度; the decision date is not stated.
独立行政法人エネルギー・金属鉱物資源機構 (JOGMEC)
Source-stated terms
- 申請者負担額の1/2を上限 独立行政法人エネルギー・金属鉱物資源機構 (JOGMEC)
Programme-wide maximum grant rate, as stated in JOGMEC's 助成率 table. It is not an exact subsidy-to-total-project-cost ratio for this plan.
The amount is approximate as both lists print it (約, "about"); the yen figure is 億円 × 100,000,000. Lifecycle review on 3 October 2026 retains decided status and an unknown grant-decision date. The 9 April recipient release adds an announced physical project near Toyama Works and a first-half FY2028 operating target. Its approximately JPY 15.9 billion investment plan is separate from the approximately JPY 7.5 billion public grant. The reviewed sources do not establish grant cash receipt, construction commencement or operation.
Full financial instrument, conditions and field-level evidenceCapital stack
One layer per value role. Public commitments and joint-vehicle capital are reported separately by currency. Other categories appear individually.
Public commitments
1 row, summed per currency
Committed to a recipient by a government or public enterprise, at the status each row states. A contracted, partially disbursed or disbursed row is binding because an agreement is executed; payment is tracked separately by status. A contracted row need not mean funds are obligated or paid, and a partially disbursed row is not fully paid. Summed per currency and per instrument, never across either; a part is never added to its package.
JPY
Grant1 row
Not yet binding
- Approximately
- 7.5 billion
1 counted
株式会社アライドマテリアル
New tungsten reduction and carburisation facilities to raise production of tungsten powder and tungsten carbide powder.
aboutJPY7.5 billionDecided18 Mar 2026- Providing government
- JP
- Value role
- Commitment
- Instrument
- Grant
- Capital source
- Public
- Supply-chain stages
- Processing
- Coding note
- Ambiguity noted
Source-reviewed industrial observations
This undertaking currently lacks a published source-reviewed industrial milestone. Any activity described in financing entries remains attributed to its publisher. Its operational status requires further source review.
Policy context
These policy actions directly parent the project's finance or designation entries. Their presence does not establish a causal effect on industrial activity.
18 Mar 2026 · Active
Certification of Allied Material's critical-minerals supply-assurance plan for tungsten under the Economic Security Promotion Act
METI / JOGMEC
Designations
Scheme recognition records standing; capital support requires a separate financial instrument.
タングステンの還元及び炭化設備を新設し、タングステン粉末及び炭化タングステン粉末の生産能力を向上させる。
Certified supply-assurance plans for critical minerals (Economic Security Promotion Act)
Recognized18 Mar 2026- Recorded in
- 2025重要鉱物第2号-1
- Supply-chain stages
- Processing
Control clauses on the same materials and stages
Clauses whose covered items share a material and a supply-chain stage with this project, with their legal status on 12 Nov 2026. The overlap is a shared material and stage; project-level effects require separate evidence.
- In force
What remains unknown
Gaps describe what Stratellar has documented. They do not establish that an activity did not occur.
- No project-native source-reviewed industrial milestone is published. Attributed activity in financing histories remains a separate evidence class; no exact milestone date or facility-wide conclusion is inferred.
- Historical amount review is incomplete. Current amounts cannot be read as a time series of earlier commitments.
- Structural links and shared materials do not demonstrate that a government measure caused an industrial outcome.
Evidence
経済産業省 (Ministry of Economy, Trade and Industry, Japan)
- Fields supported
- Name · Sponsors · Materials
- Evidence level
- Explicit
- Location in document
- Section 4, plan 2025重要鉱物第2号-1
- Qualification
- "タングステンの還元及び炭化設備を新設し、タングステン粉末及び炭化タングステン粉末の生産能力を向上させる。"
経済産業省 (Ministry of Economy, Trade and Industry, Japan)
- Fields supported
- Supply-chain stages
- Evidence level
- Ambiguous
- Location in document
- Section 4, plan 2025重要鉱物第2号-1
- Qualification
- 還元及び炭化 (reduction and carburisation) into tungsten and tungsten carbide powder is read as processing.
タングステンの供給能力を約1.5倍に増強 総額約159億円を投資、2028年度上期稼働へ
株式会社アライドマテリアル (A.L.M.T. Corp.)
- Fields supported
- Location
- Evidence level
- Explicit
- Location in document
- Page 1, new-site paragraph
- Qualification
- A site of approximately 40,000 square metres was secured about 1 km from the recipient's Toyama Works for the new powder plant.
| Source | Fields supported | Evidence level | Location |
|---|---|---|---|
| 重要鉱物(経済安全保障推進法に基づく認定供給確保計画) 経済産業省 (Ministry of Economy, Trade and Industry, Japan) · Source dossier |
| Explicit "タングステンの還元及び炭化設備を新設し、タングステン粉末及び炭化タングステン粉末の生産能力を向上させる。" | Section 4, plan 2025重要鉱物第2号-1 |
| 重要鉱物(経済安全保障推進法に基づく認定供給確保計画) 経済産業省 (Ministry of Economy, Trade and Industry, Japan) · Source dossier |
| Ambiguous 還元及び炭化 (reduction and carburisation) into tungsten and tungsten carbide powder is read as processing. | Section 4, plan 2025重要鉱物第2号-1 |
| タングステンの供給能力を約1.5倍に増強 総額約159億円を投資、2028年度上期稼働へ 株式会社アライドマテリアル (A.L.M.T. Corp.) · Source dossier |
| Explicit A site of approximately 40,000 square metres was secured about 1 km from the recipient's Toyama Works for the new powder plant. | Page 1, new-site paragraph |
For citations, open a parent policy action for BibTeX, RIS and CSL formats. Cite original documents for claims about government action.