United States Antimony Corporation

Thompson Falls antimony processing and refining expansion

  • USUnited States
  • U.S. Department of War
  • fin-us-dow-usac-antimony-2026-thompson-falls

Partially disbursedDate not stated


Value role
Commitment
Instrument
Grant
Capital source
Public
Amount as stated
“$20 million for Thompson Falls”USD
Provider
U.S. Department of WarU.S. Department of DefenseGovernment body
Recipient
United States Antimony CorporationUnited States Antimony CorporationCompany
Legal authority
Defense Production Act Title III
Programme
None named
Project
Thompson Falls antimony processing and refining expansionThompson Falls antimony processing and refining expansion
Facility
Not stated
Location
Thompson Falls, MontanaUS
Stages
Processing, RefiningSeveral stages, split not stated
Materials
AntimonyTracked materials only

Amount

USD20 million

As stated “$20 million for Thompson Falls”

USD 20,000,000 · Exact · Currency read from the issuing government

Status

Financial and physical progress are separate histories. The last entry is current.

Financial

  1. Decided

    Part of the $27M award announced for February 24; its precise $20M allocation is disclosed later by the company.

    U.S. Department of War

  2. Partially disbursedCurrent

    The filing states $12.8M received in April 2026 for accepted milestones, recognized against Thompson Falls construction in progress; no exact day is given.

    United States Antimony Corporation / U.S. Securities and Exchange Commission (EDGAR)

Implementation

  1. ConstructionCurrent

    Issuer-reported: the recipient's Q2 2026 Form 10-Q states that "The Thompson Falls facility expansion was substantially completed" and still carries project costs in construction in progress at June 30, 2026; no progress day is stated. This records physical construction only. It does not change the $20M allocation, assert obligation of that amount, or extend the $12.8M April receipt to the full grant, and it is not full commissioning or operation.

    United States Antimony Corporation / U.S. Securities and Exchange Commission (EDGAR)

Place in the money chain

Parent packages and drawn amounts are reconciled to count each underlying instrument once.

This row is part of

  • United States Antimony Corporation

    Thompson Falls facility expansion and related Alaska antimony mining integration

    USD27 millionPartially disbursed24 Feb 2026
    Providing government
    US
    Value role
    Commitment
    Instrument
    Grant
    Capital source
    Public
    Supply-chain stages
    Mining, Processing, Refining

Stated by United States Antimony Corporation / U.S. Securities and Exchange Commission (EDGAR)Q&A: CEO response on the $27M DPA award split

This geographic allocation is part of the parent $27M award, not incremental funds.

How to read this page

Evidence and status

Figure type
CommitmentMoney, or a money-like promise, committed to a named recipient or project. The only role ever summed.
Legal status
Partially disbursedSome of the money has been paid out.
Payment
Payment evidenceThe source-linked current status records partial payment. It does not establish that the full stated amount was paid or that construction occurred.
Linked projects
Project attributionOne registered project is linked directly to this row. The link alone does not prove the amount was paid or that the project advanced.

This is a commitment role, but the financial status still determines legal standing and payment. Funding and verified industrial outcomes remain separate. Construction, commissioning and production require separate physical-progress evidence. Read Stratellar's counting and evidence rules.

Notes

The recipient's SEC-furnished earnings-call transcript allocates $20M to Thompson Falls. Its Form 10-Q reports $12.8M of accepted milestones received in April 2026 and recorded against Thompson Falls construction in progress. Neither amount is incremental to the parent $27M award.

Evidence

  1. Department of War Invests $27M for the Domestic Excavation, Extraction, Processing, and Refinement of Antimony

    U.S. Department of War

    Fields supported
    Instrument · Value role · Capital source · Provider · Legal authority · Recipient · Project · Location · Supply-chain stages · Materials · Status
    Evidence level
    Explicit
    Location in document
    Opening and award-scope paragraphs
    Qualification
    Government names two work streams under one $27M DPA award; it does not state their individual amounts.
    View source dossier
  2. United States Antimony Corporation, First Quarter 2026 Earnings Call Transcript (Exhibit 99.1 to Form 8-K)

    United States Antimony Corporation / U.S. Securities and Exchange Commission (EDGAR)

    Fields supported
    Amount · Related commitments · Project · Location
    Evidence level
    Explicit
    Location in document
    May 2026 SEC-furnished transcript: CEO answer to Jonathan Miller's funding allocation question
    Qualification
    Company explicitly identifies the $20M Thompson Falls and $7M Alaska split. Does not establish separate obligations or disbursement.
    View source dossier
  3. United States Antimony Corporation, Form 10-Q for the quarter ended June 30, 2026

    United States Antimony Corporation / U.S. Securities and Exchange Commission (EDGAR)

    Fields supported
    Status · Project · Location
    Evidence level
    Explicit
    Location in document
    Note 9 — Government Grant and Property, Plant and Equipment; Note 16 — Thompson Falls, Montana Facility Expansion
    Qualification
    Confirms payment of $12.8M in April 2026, not the entire Thompson Falls $20M allocation. Notes 9 and 16 also support the issuer-reported construction status (expansion substantially completed; costs still in construction in progress at June 30, 2026).
    View source dossier