MP 10X Development, LLC (project company established to develop the 10X Facility)

Second domestic magnet manufacturing facility

  • USUnited States
  • US Department of Defense
  • fin-us-dod-mp-2025-magnet-offtake

Contracted


Value role
Commitment
Instrument
Offtake
Capital source
Public
Amount as stated
Not stated
Provider
US Department of DefenseU.S. Department of DefenseGovernment body
Recipient
MP 10X Development, LLC (project company established to develop the 10X Facility)MP 10X Development, LLCProject company
Legal authority
Not stated
Programme
None named
Project
Second domestic magnet manufacturing facility10X Facility
Facility
10X Facility
Location
Not stated
Stages
Component manufacturingSingle stage
Materials
Rare-earth permanent magnets (NdFeB)Tracked materials only

Amount

The source states this instrument’s terms but leaves the amount unspecified.

Status

Financial and physical progress are separate histories. The last entry is current.

Financial

  1. ContractedCurrent

    Offtake Agreement dated 9 July 2025 (Exhibit 10.5).

    MP Materials Corp. / U.S. Securities and Exchange Commission (EDGAR)

Implementation

  1. Announced

    The company "will construct" the facility "at a soon-to-be-chosen location".

    MP Materials

  2. ConstructionCurrent

    "In April 2026, the Company purchased a 120-acre site in Northlake, Texas, for approximately $80 million where construction of the 10X Facility is currently underway." Reported for the quarter to 30 June 2026; the start date of construction is not stated.

    MP Materials Corp. / U.S. Securities and Exchange Commission (EDGAR)

How to read this page

Evidence and status

Figure type
CommitmentMoney, or a money-like promise, committed to a named recipient or project. The only role ever summed.
Legal status
ContractedA binding agreement has been executed. Not a payment, and not necessarily an obligation of funds: an agreement can leave that to a later step.
Payment
Payment evidenceThis status does not itself establish a cash payment. In particular, a signed contract does not necessarily establish an obligation of funds.
Linked projects
Project attributionOne registered project is linked directly to this row. The link alone does not prove the amount was paid or that the project advanced.

This is a commitment role, but the financial status still determines legal standing and payment. Funding and verified industrial outcomes remain separate. Construction, commissioning and production require separate physical-progress evidence. Read Stratellar's counting and evidence rules.

Terms

Stated outcomes

Who says it matters: a company target is not a government commitment.

  • Target date

    Stated by the recipient

    2028

    “expected to begin commissioning in 2028”

    MP Materials

  • Annual capacity

    Stated by the recipient

    approximately 10,000 metric tons

    “MP Materials' total U.S. rare earth magnet manufacturing capacity will reach an estimated 10,000 metric tons”

    Company-wide magnet capacity once the facility is complete, not the 10X Facility alone.

    MP Materials

Notes

No amount is stated for the offtake itself: DoD buys at the Project Company's production cost and makes facilitation payments. The outcomes are the company's expectations. Lifecycle review on 3 October 2026 retains contracted status and construction with an unknown commencement date. The Q2 2026 filing recognizes pre-production reimbursable costs under the offtake but does not separately quantify cumulative cash paid under it; no disbursement status or total commitment amount is inferred from deferred balances or receivables. Price Protection Agreement receipts, Independence production and Apple prepayments concern separate instruments or facilities. Commissioning in 2028 remains a target.

Evidence

  1. MP Materials Corp., Form 8-K (Transaction Agreement with the Department of Defense)

    MP Materials Corp. / U.S. Securities and Exchange Commission (EDGAR)

    Fields supported
    Instrument · Value role · Capital source · Provider · Recipient · Project · Facility · Supply-chain stages · Materials · Status · Terms
    Evidence level
    Explicit
    Location in document
    Item 1.01, Offtake Agreement
    View source dossier
  2. MP Materials announces transformational public-private partnership with the Department of Defense

    MP Materials

    Fields supported
    Status · Outcomes
    Evidence level
    Explicit
    Location in document
    Opening paragraphs
    View source dossier
  3. MP Materials Corp. Form 10-Q for the quarterly period ended June 30, 2026

    MP Materials Corp. / U.S. Securities and Exchange Commission (EDGAR)

    Fields supported
    Status
    Evidence level
    Explicit
    Location in document
    Note 1; Note 6, Property, Plant and Equipment; Note 9, Operating Leases; Note 13, Other Current Assets; MD&A, DoW Offtake Agreement and Magnetics segment
    Qualification
    Construction is underway and the filing continues to describe the executed DoW offtake. The $6.0 million contract liability and $3.892 million reimbursable-cost receivable are accounting balances, not a separately disclosed cumulative cash-disbursement amount for this offtake.
    View source dossier
  4. MP Materials Reports Second Quarter 2026 Results

    MP Materials Corp.

    Fields supported
    Status
    Evidence level
    Explicit
    Location in document
    CEO comments in second-quarter 2026 results
    Qualification
    Reports accelerated construction at 10X. This corroborates the project's construction status; it does not date construction commencement or establish a financing draw.