  "projectionVersion": "smpt-investigation-1",
  "projectId": "prj-ca-marathon-copper-palladium",
  "corpus": {
    "revision": "2026-11-12",
    "legalStatusCutoff": "2026-11-12",
    "view": "current_corpus_revision",
    "notice": "Curated corpus revision, not source freshness or historical known-as-of coverage. Financial histories retain their own status dates."
  },
  "project": {
    "id": "prj-ca-marathon-copper-palladium",
    "name": "Marathon copper-palladium project",
    "sponsorOrgIds": [
      "org-ca-generation-mining"
    ],
    "locations": [
      {
        "countryCode": "CA",
        "subnational": "Ontario",
        "asStated": "Marathon, Northwestern Ontario"
      }
    ],
    "stages": [
      "mining"
    ],
    "materialIds": [
      "copper",
      "palladium"
    ],
    "materialAttribution": "tracked_only",
    "untrackedMaterialsAsStated": [],
    "evidence": [
      {
        "sourceId": "src-cgf-marathon-2026",
        "supports": [
          "name",
          "sponsors",
          "location",
          "stages",
          "materials"
        ],
        "evidence": "explicit",
        "locator": "Opening paragraphs and transaction details",
        "note": null
      },
      {
        "sourceId": "src-ca-genm-marathon-construction-2026",
        "supports": [
          "stages"
        ],
        "evidence": "explicit",
        "locator": "Issuer statement of construction commencement and Early Works Program",
        "note": "Construction-phase early works were underway by the 1 October 2026 publication date; this does not establish production, commissioning or a specific exact first-work date."
      }
    ],
    "notes": "At the initial 14 September 2026 financing announcement Marathon was described as fully permitted and shovel-ready. Generation Mining subsequently reported early construction work had commenced by 1 October 2026, including site access, clearing and water-management preparations. This is a documented construction-phase project milestone, separate from a commercial production date."
  },
  "organizations": [
    {
      "id": "org-ca-canada-growth-fund",
      "name": "Canada Growth Fund",
      "nameOriginal": null,
      "aliases": [],
      "kind": "public_financier",
      "roles": [
        {
          "role": "provider",
          "recordId": "fin-ca-cgf-marathon-equity-2026"
        },
        {
          "role": "provider",
          "recordId": "fin-ca-cgf-marathon-note-2026"
        }
      ],
      "evidence": [
        {
          "sourceId": "src-nrcan-g7-cmpa-2025",
          "supports": [
            "name",
            "kind",
            "country",
            "actor"
          ],
          "evidence": "ambiguous",
          "locator": "Nouveau Monde Graphite paragraph; Rio Tinto paragraph",
          "note": "Named as the source of investments and an \"equity-like royalty investment\" in a Government of Canada announcement; the backgrounder does not describe its ownership."
        }
      ]
    },
    {
      "id": "org-ca-generation-mining",
      "name": "Generation Mining Limited",
      "nameOriginal": null,
      "aliases": [],
      "kind": "company",
      "roles": [
        {
          "role": "registered_sponsor",
          "recordId": "prj-ca-marathon-copper-palladium"
        },
        {
          "role": "recipient",
          "recordId": "fin-ca-cgf-marathon-equity-2026"
        },
        {
          "role": "recipient",
          "recordId": "fin-ca-cgf-marathon-note-2026"
        }
      ],
      "evidence": [
        {
          "sourceId": "src-cgf-marathon-2026",
          "supports": [
            "name",
            "kind",
            "country"
          ],
          "evidence": "explicit",
          "locator": "Opening paragraphs and company description",
          "note": null
        }
      ]
    }
  ],
  "financialInstruments": [
    {
      "id": "fin-ca-cgf-marathon-equity-2026",
      "eventId": "evt-ca-cgf-marathon-2026",
      "instrument": "equity",
      "valueRole": "commitment",
      "capitalSource": "public_enterprise",
      "projectRelationship": "directly_attributable",
      "projectId": "prj-ca-marathon-copper-palladium",
      "associatedProjectIds": [],
      "amount": {
        "value": "90000000",
        "currency": "CAD",
        "qualifier": "approximately",
        "amountAsStated": "~ $90 million",
        "currencyBasis": "issuer_context",
        "basisNote": null,
        "basisLabel": null
      },
      "amountBasis": "current_recorded_terms_not_historical_totals",
      "provider": "Canada Growth Fund",
      "providerJurisdiction": "canada",
      "providerOrgIds": [
        "org-ca-canada-growth-fund"
      ],
      "recipient": "Generation Mining Limited",
      "recipientOrgIds": [
        "org-ca-generation-mining"
      ],
      "programmeId": null,
      "legalAuthority": null,
      "facility": null,
      "locations": [
        {
          "countryCode": "CA",
          "subnational": "Ontario",
          "asStated": "Northwestern Ontario"
        }
      ],
      "materialIds": [
        "copper",
        "palladium"
      ],
      "stages": [
        "mining"
      ],
      "currentFinancialStatus": "disbursed",
      "financialStatusHistory": [
        {
          "status": "announced",
          "date": "2026-09-14",
          "sourceId": "src-cgf-marathon-2026",
          "note": null
        },
        {
          "status": "disbursed",
          "date": "2026-09-21",
          "sourceId": "src-ca-genm-cgf-equity-close-2026",
          "note": "Issuer confirms completed issuance of CGF's C$40m private placement shares and approximately C$49m bought-deal shares. The actual combined value of roughly C$89m reconciles to CGF's earlier approximately C$90m announcement; preserve its original approximate amount."
        }
      ],
      "legacyPhysicalObservations": [
        {
          "status": "construction",
          "date": null,
          "sourceId": "src-ca-genm-marathon-construction-2026",
          "note": "Issuer confirmed Marathon early-works construction had commenced by 1 October 2026; exact first-work day is unstated. The project milestone is separate from the timing of CGF equity payment and the convertible note."
        }
      ],
      "terms": [],
      "statedOutcomes": [],
      "relationships": [],
      "evidence": [
        {
          "sourceId": "src-cgf-marathon-2026",
          "supports": [
            "instrument",
            "value_role",
            "capital_source",
            "amount",
            "provider",
            "status",
            "recipient",
            "project",
            "location",
            "stages",
            "materials"
          ],
          "evidence": "explicit",
          "locator": "Financing paragraphs",
          "note": null
        },
        {
          "sourceId": "src-ca-genm-cgf-equity-close-2026",
          "supports": [
            "amount",
            "status",
            "recipient",
            "project"
          ],
          "evidence": "explicit",
          "locator": "Closing and CGF acquisition paragraphs",
          "note": "Closing evidence: C$40m private placement plus approximately C$49m bought-deal CGF shares, versus earlier ~C$90m commitment."
        },
        {
          "sourceId": "src-ca-genm-marathon-construction-2026",
          "supports": [
            "status"
          ],
          "evidence": "explicit",
          "locator": "Opening and Early Works Program",
          "note": "Physical construction at Marathon; no inference about note issuance, further drawdowns or commercial production."
        }
      ],
      "notes": "CGF's approximately C$90m announced equity commitment was completed through a C$40m private placement and approximately C$49m acquisition in the bought-deal offering, confirmed on 21 September 2026. The original approximate headline is retained, rather than replacing it with an exact C$90m cash receipt. The issuer subsequently reported early works underway at Marathon by 1 October 2026; the exact first construction day is unstated. This equity closing does not establish issuance of CGF's separately proposed C$50m convertible note."
    },
    {
      "id": "fin-ca-cgf-marathon-note-2026",
      "eventId": "evt-ca-cgf-marathon-2026",
      "instrument": "unspecified",
      "valueRole": "commitment",
      "capitalSource": "public_enterprise",
      "projectRelationship": "directly_attributable",
      "projectId": "prj-ca-marathon-copper-palladium",
      "associatedProjectIds": [],
      "amount": {
        "value": "50000000",
        "currency": "CAD",
        "qualifier": "exact",
        "amountAsStated": "$50 million",
        "currencyBasis": "issuer_context",
        "basisNote": null,
        "basisLabel": null
      },
      "amountBasis": "current_recorded_terms_not_historical_totals",
      "provider": "Canada Growth Fund",
      "providerJurisdiction": "canada",
      "providerOrgIds": [
        "org-ca-canada-growth-fund"
      ],
      "recipient": "Generation Mining Limited",
      "recipientOrgIds": [
        "org-ca-generation-mining"
      ],
      "programmeId": null,
      "legalAuthority": null,
      "facility": null,
      "locations": [
        {
          "countryCode": "CA",
          "subnational": "Ontario",
          "asStated": "Northwestern Ontario"
        }
      ],
      "materialIds": [
        "copper",
        "palladium"
      ],
      "stages": [
        "mining"
      ],
      "currentFinancialStatus": "announced",
      "financialStatusHistory": [
        {
          "status": "announced",
          "date": "2026-09-14",
          "sourceId": "src-cgf-marathon-2026",
          "note": null
        }
      ],
      "legacyPhysicalObservations": [],
      "terms": [],
      "statedOutcomes": [],
      "relationships": [],
      "evidence": [
        {
          "sourceId": "src-cgf-marathon-2026",
          "supports": [
            "instrument",
            "value_role",
            "capital_source",
            "amount",
            "provider",
            "status",
            "recipient",
            "project",
            "location",
            "stages",
            "materials"
          ],
          "evidence": "explicit",
          "locator": "Financing paragraphs",
          "note": null
        }
      ],
      "notes": "The 14 September source describes a C$50m convertible note within a proposed C$100m offering, with shareholder and regulatory closing conditions. The 21 September issuer release confirms CGF common-share purchases, not the convertible note closing. SMPT's instrument taxonomy lacks a convertible-debt subtype; keep the instrument unspecified and financial status announced pending direct evidence of issuance."
    }
  ],
  "nonallocativeAssociations": [],
  "designations": [],
  "nativeMilestones": [
    {
      "id": "mil-ca-marathon-early-works-construction-started",
      "projectId": "prj-ca-marathon-copper-palladium",
      "kind": "construction_started",
      "claimMode": "occurred",
      "evidenceCategory": "reviewed_project_native",
      "scope": "bounded_project_workstream",
      "scopeAsStated": "early works program at the Marathon copper-palladium project",
      "occurredOn": null,
      "targetOn": null,
      "sourceId": "src-ca-genm-marathon-construction-2026",
      "locator": "Opening paragraphs of the 1 October 2026 Generation Mining release",
      "statementOriginal": "Early works have commenced following the posting of the construction phase financial assurance under the Project's filed Closure Plan.",
      "statementEn": "Early works have commenced following the posting of the construction phase financial assurance under the Project's filed Closure Plan.",
      "statementEnSource": "na",
      "reviewedBy": "Benjamin Yang",
      "reviewedAt": "2026-11-08",
      "note": "Issuer statement published 1 October 2026; it establishes that early works had begun by that date, not the first day of work, so occurredOn stays null. The scope is the bounded early-works programme, not construction of the full mine. The Canada Growth Fund equity row is cross-referenced only: this milestone does not date, condition or evidence any CGF disbursement, and no financing causality is inferred."
    }
  ],
  "policyContexts": [
    {
      "id": "evt-ca-cgf-marathon-2026",
      "relationship": "finance_or_designation_parent",
      "jurisdiction": "canada",
      "issuingBody": "Canada Growth Fund Inc.",
      "titleEn": "Canada Growth Fund commits approximately C$140 million to Generation Mining for Marathon",
      "titleOriginal": "Canada Growth Fund commits approximately C$140 million to Generation Mining for Marathon",
      "documentNumber": null,
      "date": "2026-09-14",
      "policyStatus": "active",
      "sourceIds": [
        "src-cgf-marathon-2026"
      ]
    }
  ],
  "coannouncedControls": [],
  "financePackageReferences": [],
  "unknowns": [
    "Reviewed observations establish only their stated scope. They do not by themselves establish sustained construction, capacity achieved, commercial output or a financing payout.",
    "Historical amount review is incomplete. Current amounts cannot be read as a time series of earlier commitments.",
    "Structural links and shared materials do not demonstrate that a government measure caused an industrial outcome."
  ],
  "sources": [
    {
      "id": "src-ca-genm-cgf-equity-close-2026",
      "title": "Generation Mining closes bought-deal offering and concurrent private placement for C$240 million",
      "publisher": "Generation Mining Limited",
      "url": "https://genmining.com/news/2026/generation-mining-closes-bought-deal-public-offe-15459/",
      "language": "en",
      "sourceType": "other",
      "confidence": "primary",
      "publishedOn": "2026-09-21",
      "accessedOn": "2026-11-06"
    },
    {
      "id": "src-ca-genm-marathon-construction-2026",
      "title": "Generation Mining commences construction at Marathon copper-palladium mine",
      "publisher": "Generation Mining Limited",
      "url": "https://genmining.com/news/2026/generation-mining-commences-construction-at-marath-15486/",
      "language": "en",
      "sourceType": "other",
      "confidence": "primary",
      "publishedOn": "2026-10-01",
      "accessedOn": "2026-11-06"
    },
    {
      "id": "src-cgf-marathon-2026",
      "title": "Canada Growth Fund commits to invest approximately $140 million in Generation Mining",
      "publisher": "Canada Growth Fund Inc.",
      "url": "https://www.cgf-fcc.ca/en/news/canada-growth-fund-commits-to-invest-140-million-in-generation-mining-to-mobilize-private-capital-for-ontarios-marathon-critical-minerals-project/",
      "language": "en",
      "sourceType": "official",
      "confidence": "primary",
      "publishedOn": "2026-09-15",
      "accessedOn": "2026-11-05"
    },
    {
      "id": "src-nrcan-g7-cmpa-2025",
      "title": "Backgrounder: Canada unlocks 26 new investments and partnerships with 9 allied countries to secure critical minerals supply chains",
      "publisher": "Natural Resources Canada",
      "url": "https://www.canada.ca/en/natural-resources-canada/news/2025/10/backgrounder-canada-unlocks-25-new-investments-and-partnerships-with-9-allied-countries-to-secure-critical-minerals-supply-chains.html",
      "language": "en",
      "sourceType": "official",
      "confidence": "primary",
      "publishedOn": "2025-10-31",
      "accessedOn": "2026-09-23"
    }
  ],
  "limitations": [
    "Policy contexts here parent existing finance or designation records; a shared material or date never creates a causal edge.",
    "Coannounced controls are announcement siblings only, not project-specific restrictions or effects.",
    "Direct project attribution and nonallocative association are different. No individual monetary allocation, financial sum or payment conclusion is authorized.",
    "Financing statuses describe the current corpus revision. Legacy implementation observations require scoped review and are not project-native milestones.",
    "A milestone's event/target date, publication/access horizon and reviewer date are separate. A planned target is not automatically occurred.",
    "An absent reviewed milestone means no approved entry in Stratellar, not that the facility is inactive or failed.",
    "Amounts retain current source-stated terms, original currency and exact decimal strings. This packet computes no historical financial totals or project-wide monetary allocation.",
    "Published source review does not establish independent on-site verification. Source, financial-status, occurrence, target and review dates remain distinct."
  ]
}